PROJECT COST AND ECONIMICS.

Now you will get an over-view on the cost and economics of Ghazi Barotha Hydro Power Project. It will be completed by the year 2001. The total cost of the project is about 2.2 billion US dollars. Foreign exchange loan will constitute about 56 % of the total cost will the remaining 44 % will be provided by the Governement of Pakistan.

Total foreign exchange loan : 250 Million US $

FINANCER

AMOUNT, US $

( million )

%AGE OF
LOAN

%AGE OF TOTAL
COST

World Bank

350 28 15.9

Japan

350 28 15.9

Asian Development

Bank

300 24 13.6

Germany

150 12 6.8

European Investment

Bank

60 4.8 2.7

Islamic Development

Bank

40 3.2 1.8

This table showas that the major financers are Japan and the World Bank. Each is providing 250 million US $ i.e., 28 % of the foreign exchange loan and 15.0 % of the total cost of the project.

  1. The cost estimates are based on July 1990 price levels and at an exchange rate of Rs. 22 per US $.
  2. Most prices were estimated by analytical methods, although few were based upon previous estimates or other past experiences, with appropriate adjustment.
  3. The cost calculation were divided into local and foreign currency components.
  4. Labour, cement, reinforcing steel, electricity, fuel and lubricants were considered as local costs and the market prices for these items were used.
  5. Equipment, spare parts, M & E palnt and equipment were considered as foregin costs.
  6. Tools, materials and supplies were considered to have a 25 % local and 75 % foreign currency comoponens.
  7. Custom duties and taxes on imported equipment are not included in these estimates.

* Since, the exchange rate of US $ in Pakistani Rupee has risen considerably, as compared to the exchange rate discussed above, so the total cost has changed accordingly.

ESTIMATED COST

  EXPRESSED IN US $ MILLION   EXPRESSES IN Rs. MILLLION      
Description LOCAL CURRENCY

COMPONENT

FOREIGN CURRENCY

COMPONENT

TOTAL LOCAL CURRENCY

COMPONENT

FOREIGN CURRENCY

COMPONENT

TOTAL
Land Acquisiti- on & Relocation 51.08 6.31 57.39 1123.76 138.82 1262.58
Preparato- ry Works 26.55 25.45 52.00 584.32 559.9 1144.00
Power House 2.89 17.15 20.04 63.58 377.30 440.88
Barrage 115.66 417.97 533.63 2544.52 9195.34 11739.86
Power Channel 162.79 547.88 710.67 3581.38 12053.36 15634.74
Power Complex 180.58 645.65 826.23 3972.66 14209.36 18177.06

Khwarzimic Science Society
Centre of Excellence in Solid State Physics
University of Punjab, Quaid-e-Azam Campus
Lahore-54590, Pakistan
Ph: +9242-5864185, Fax: +9242-5864534
Email: info@khwarzimic.org